INSTALLING HUNDREDS OF SEALS IN BUFFALO NEW YORK
Project Update
Icon WriterCaleb Rutledge, 3/22/2022

HydraTech has been working on miles of cast-iron pipes below Buffalo New York for about a year now. The first two phases of the project are complete with approximately 350 seals being installed during these phases. The third and final stage will start soon, which is expected to include the installation of 160 seals.

 

Four images, pipe entrance, opening to a pipe, looking down a pipe, HydraTite installed over a joint in a pipe

The aging pipes have joints experiencing separation and offset, with ranging severity. Some joints are separated as little as half an inch and others are separated by about three inches. HydraTech assesses each of the joints and seals them with appropriately sized HydraTite. In joints that are further separated backing plates are utilized. These backing plates are also used to close off unused branches in the pipe.

Looking down the pipe towards an exposed joint
A seal protecting a joint
an uncovered, open pipe
Pipe access point
orange emblem, 'Update!'

HydraTech recently completed this project. Click to read the updated blog here >

SHARE NOW

LinkedIn logo  Facebook logo  Twitter logo  Instagram logo
HydraTech employees gathering for potluck

Last Post:
FRIDAY POTLUCK

Peter and Caleb Standing In Front Of The HydraTech Booth At OTEC

Next Post:
TRAVELING TO LYNNWOOD WASHINGTON FOR A HYDRATITE INSTALLATION DEMONSTRATION